Aggreko Mutundwe thermal plant project

Sector: Geothermal • Location: Uganda

Source: World Bank Group

Project
Distressed

In August 2007, the Government of Uganda procured Aggreko to implement a 50MW thermal plant at Mutundwe under a 3-year rental contract. This emergency power supply contract was supported by the World Bank.

The award followed a competititve bidding process initiated in 2006. Four companies participated to the bidding process: Unatrac International, Jacobsen AS Elecktro, MFK Corporation and Aggre

Project Information FAQ

Project Information

4 Q
The project “Aggreko Mutundwe thermal plant project” is an infrastructure initiative in the Geothermal sector, located in Uganda. Taiyo aggregates data on it from World Bank Group.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

distressed

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

In August 2007, the Government of Uganda procured Aggreko to implement a 50MW thermal plant at Mutundwe under a 3-year rental contract. This emergency power supply contract was supported by the World Bank. The award followed a competititve bidding process initiated in 2006. Four companies participated to the bidding process: Unatrac International, Jacobsen AS Elecktro, MFK Corporation and Aggreko International. The implementation agreement and the power purchase agreement were signed in January 2008 in Kampala. Under the agreement, the plant was expected to run for 18-hours daily under the power purchase agreement. The equipment for the contract was expected to be installed in phases and commissioned during the second quarter of 2008. The estimated investment for the rental power plants was determined by calculating an equivalent annual depreciation per MW and multiplying it by the number of years in the contract. We have used the following assumptions for this estimate: US$600 per kW as estimated investment, 15 years as expected asset life, and 10 percent as the annual discount (return) rate. Mutundwe power plant was shut down by Aggreko in November 2011 following financial disputes with the government. By 2012, the government had decommissioned the Mutundwe plant. Project in distress following a financial dispute between Aggreko plc and GoU. Plant shut down as a consequence in November. Plant decommissioned by March 2012.

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data