Bao Loc VRG JSC was planning the development of the 24.5MW Bao Loc Hydropower Plant, Bao Lam and Di Linh districts, Lam Dong province. The project was expected to generate 106,501.5 MWh annually, to be supplied to the national grid via a 110kV transmission line at a load factor of 49.6%.

The project was to consist of two Vertical Shaft Francis turbines of 12.63MW each and two vertical acis sus

Project Information FAQ

Project Information

4 Q
The project “Bao Loc Hydropower Plant” is an infrastructure initiative in the Hydro sector, located in Vietnam. Taiyo aggregates data on it from World Bank Group.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

active

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

Bao Loc VRG JSC was planning the development of the 24.5MW Bao Loc Hydropower Plant, Bao Lam and Di Linh districts, Lam Dong province. The project was expected to generate 106,501.5 MWh annually, to be supplied to the national grid via a 110kV transmission line at a load factor of 49.6%. The project was to consist of two Vertical Shaft Francis turbines of 12.63MW each and two vertical acis suspended generators of 12.25MW each. Commissioning was expected for 2012. The feasibility study was completed in August 2009 and aproved in November 2009. The EIA was approved in December 2009. The equipment supply contract was signed in July 2010. Electricity tariff was VND 681 per kWh ($0.0327 per kWh). The debt/equity ratio was 55/45. Total investment was estimated at VND 604,850 million ($29.0 million). Total debt was VND 332.668 million, total equity was VND 272,183 million. WACC was 12.17%. The project also received a tax break, of 0% until year 6, 12.5% for the following 9 years and 25% after that. Operational life was expected at 30 years. CERs were sold at EUR10 ($13.1). Financial closure date was unknown, estimated ehre was July 2010 (signing equipment supply contract). http://cdm.unfccc.int/filestorage/L/Z/J/LZJY5CQX1GE4TAKS9MVPDNRUBW2I07/PDD.pdf?t=OEl8bTI3eHBnfDAQFgGpPondH8Tgp4w8Me72

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data