BC Hydro Customer Connection Project: ARC Resources Electrification

Sector: Steel • Location: British Columbia, Canada

Source: Infrastructure Canada

Project
In Progress

The BC Hydro Customer Connection Project: ARC Resources Electrification (the project) includes the construction of one tap for the Attachie project, and the installation of a fourth transformer within BC Hydro’s Bear Mountain Terminal substation to supply the Dawson facility. A tap is the electrical connection point between the customer’s transmission line and BC Hydro’s electricity grid. The tap

Project Information FAQ

Project Information

4 Q
The project “BC Hydro Customer Connection Project: ARC Resources Electrification” is an infrastructure initiative in the Steel sector, located in British Columbia, Canada. Taiyo aggregates data on it from Infrastructure Canada.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

in progress

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

The BC Hydro Customer Connection Project: ARC Resources Electrification (the project) includes the construction of one tap for the Attachie project, and the installation of a fourth transformer within BC Hydro’s Bear Mountain Terminal substation to supply the Dawson facility. A tap is the electrical connection point between the customer’s transmission line and BC Hydro’s electricity grid. The tap and transformer are required to supply electricity to the Attachie and Dawson natural gas processing facilities, respectively. Project works for the tap: • Construction of a 138 kilovolt tap on a BC Hydro transmission line. Work includes the following: o a single-pole vertical dead-end tap structure is proposed for connection to transmission line 1L364 o three sectionalizing switches will be installed at the tap o modifications will be required to a couple of existing BC Hydro structures and new structures will be installed o key activities for tap construction include the following: right-of-way clearing for new structures, road access to tap structures, reclamation following project completion of the tap Project works for the transformer: • Installation of a fourth 230 kilovolt:138 kilovolt stepdown transformer at the Bear Mountain Terminal substation • Work will be undertaken within the fenced yard of the substation and includes the following: o purchase and installation of a transformer o excavation and construction for a new concrete foundation for the transformer o design, supply and installation of structural steel supports for the transformer bus connections (a bus is an electrical connection between two points)

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data