Central Termoeléctrica ChilcaUno (Units1,2,3, and 4)

Sector: Wind • Location: Peru

Source: World Bank Group

Project
Active

Enersur, a subsidiary of GDF Suez [France] began developing Central Termoeléctrica ChilcaUno in September 2005. The Chilca I TPP was to have two 174 MW units and operate in an open cycle gas powered plant, the first to receive gas from the Camisea gas field. The first 174 MW unit became operational in December 2006 and the second 174 MW unit became operational in July 2007 bringing capacity to 348

Project Information FAQ

Project Information

4 Q
The project “Central Termoeléctrica ChilcaUno (Units1,2,3, and 4)” is an infrastructure initiative in the Wind sector, located in Peru. Taiyo aggregates data on it from World Bank Group.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

active

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

Enersur, a subsidiary of GDF Suez [France] began developing Central Termoeléctrica ChilcaUno in September 2005. The Chilca I TPP was to have two 174 MW units and operate in an open cycle gas powered plant, the first to receive gas from the Camisea gas field. The first 174 MW unit became operational in December 2006 and the second 174 MW unit became operational in July 2007 bringing capacity to 348MW. The project cost of was approximately US $50 million for the first unit and US $40 million for the second unit. The first unit included setup of the plant. The project included a 220kv transmission line to be connected with the national grid with definitive concession to trasmit electricity granted by Peru's MEM (energy and mines ministry) in 2006. In the first semester of 2008, the construction of a third 193 MW turbine began which became operational in the third semester of 2009. The total project cost was approximately US $90 million. The third phase involved developing the turbines into a combined cycle instead of open cycle facility and was to boost capacity to approximately 800 MW. A 270 MW vapor turbine was to be added to the existing facility. To finance the third phase, Enersur signed a US $310 million financing contract with Banco de Credito del Peru in June 2010. In January 2015, Enersur was granted the authorization to build another natural gás combined cycle generating unit with capacity of 112.8 MW. The investment in this unit was estimated at US$ 140 million. Construction works which were contracted to Duro Felguera S.A. commenced in March 2015. The unit was expected to begin commercial operations in the second semestre of 2016.

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data