Delfin LNG Second Floating LNG Vessel (FLNG2)

Sector: LNG • Location: Louisiana, United States

Source: Hart Energy

Project
Planned

Delfin Midstream issued Siemens Energy Inc. a limited notice to proceed on July 15, 2026, to begin procuring long lead equipment for a second floating LNG production vessel to be moored in the Gulf of America at Delfin LNG. The equipment includes four SGT-750 gas turbines and mixed-refrigerant compressors. This is a key milestone needed to make a final investment decision (FID) on the second FLNG

Project Information FAQ

Project Information

4 Q
The project “Delfin LNG Second Floating LNG Vessel (FLNG2)” is an infrastructure initiative in the LNG sector, located in Louisiana, United States. Taiyo aggregates data on it from Hart Energy.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

planned

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

Delfin Midstream issued Siemens Energy Inc. a limited notice to proceed on July 15, 2026, to begin procuring long lead equipment for a second floating LNG production vessel to be moored in the Gulf of America at Delfin LNG. The equipment includes four SGT-750 gas turbines and mixed-refrigerant compressors. This is a key milestone needed to make a final investment decision (FID) on the second FLNG vessel, targeted for year-end 2026. The vessel will use the same design as the first FLNG vessel (FLNG1), which reached a $5 billion FID on June 3, 2026, and is currently in the execution phase. FLNG1 is expected to begin LNG production in 2030. Both vessels will have an expected nameplate capacity of 4.4 million tonnes per annum (mtpa). The second vessel will connect to existing offshore pipeline infrastructure at the Delfin Deepwater Port, which is being expanded as part of a phased multi-vessel development. Delfin is building onshore compression facilities to support the feedgas supply to the FLNG vessels and repurposing pipelines to transport natural gas to mooring sites. Delfin has signed a 20-year sale and purchase agreement with Centrica Energy for 0.25 mtpa from FLNG2. Delfin also made an agreement with MidOcean Energy, an LNG company formed by EIG, to sell a stake in FLNG2, allowing MidOcean to acquire up to 50% interest and receive a corresponding share of LNG production. The agreement is subject to FID and other customary conditions. Delfin and MidOcean will partner on future pre-development activities to potentially bring on a third FLNG vessel, adding an additional 4.4 mtpa of capacity, for a total of up to 13.2 mtpa of LNG production.

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data