The Second Doukkala Irrigation Project for Morocco consists of: enlargement of the main supply canal over 22 km, construction of about 10 km of feeder canals and installation of automatic flow regulators; construction of six pumping stations with a total installed capacity of 11,300 kw, each with an elevated equalizing reservoir; construction of 31 km of 60 kv and 62 km of 22 kv power transmission

Status
Closed
Sector
Road, Water Supply and Storage, Power Generation (CCGT), Waste Processing and Treatment, Raw Materials, Government
Location
Morocco
Updated
22 Jul 2026
Source
World Bank Group

ConstructChat

Ask ConstructChat about DOUKKALA IRRIGATION II

Pick a question to edit it, or write your own.

First answer free · no account

I am a

Project Information FAQ

Project Information

5 Q
The project “DOUKKALA IRRIGATION II” is an infrastructure initiative in the Road sector, located in Morocco. Taiyo aggregates data on it from World Bank Group.

Participants

Sponsoring Agency

Status

Original status

closed

Taiyo status

Closed

Taiyo last update

2026-07-22

Contact

Not available for this record.

Description

Description

The Second Doukkala Irrigation Project for Morocco consists of: enlargement of the main supply canal over 22 km, construction of about 10 km of feeder canals and installation of automatic flow regulators; construction of six pumping stations with a total installed capacity of 11,300 kw, each with an elevated equalizing reservoir; construction of 31 km of 60 kv and 62 km of 22 kv power transmission lines and a substation for pumping stations; land preparation and consolidation including farm roads, windbreaks and drainage; installation of 450 km of buried pipe distribution system including hydrants, each serving about 16 ha, and associated mobile sprinkler equipment; construction of main drainage channels entailing about 300,000 cubic meters excavation; construction of 108 km of roads, reinforcement of 64 km of existing roads; and construction of buildings and provision of equipment for extension, operation, maintenance, artificial insemination, and telecommunications. This report comprises two impact evaluation reports for Mexico an Morocco, and an overview which synthesizes the findings of both impact evaluations regarding the extent of, and reasons for, sustainability a compares the impact of irrigation systems design on project performance striking feature of all four projects is the lower agricultural and performance than that estimated at the time of audit. Weaker commodity an inadequate development approach in one project, lower than expected efficiencies, insufficient attention to operation and maintenance in a projects, and damage to the environment and natural resources have been main factors affecting performance. However, with one exception, which performed poorly, the degree of success in the transfer of technology respect of both irrigation practice and agricultural productivity has continued to be sustained in the other three projects.

Original sector

Agriculture, Fishing and Forestry

Location

Country

Morocco

Source

Source

World Bank Group

URL

More Details

Record type

Project

Sector

Road, Water Supply and Storage, Power Generation (CCGT), Waste Processing and Treatment, Raw Materials, Government

Article published date

2025-12-17

More on this project

Research

Free account

View all details

You are reading the public part. A free account opens the rest:

  • Every detail on this project
  • News and media coverage
  • Technical research
View all details

Free account · no card · lands you back on this project