Fishing Development Project

Sector: Raw Materials • Location: Gambia

Source: African Development Bank (AfDB)

Project

ISSUE: The construction contract was awarded in June 1986, with a completion period of 24 months and supervision was awarded on 5th March 1986. The work physically commenced on 1st September 1986. The contractor was suspended in 1989 in order to allow Government investigation of the course of the failed sections of the road. The contract was eventually terminated. The project remains nearly 60% co

Project Information FAQ

Project Information

4 Q
The project “Fishing Development Project” is an infrastructure initiative in the Raw Materials sector, located in Gambia. Taiyo aggregates data on it from African Development Bank (AfDB).

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

Obfuscated Data

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

ISSUE: The construction contract was awarded in June 1986, with a completion period of 24 months and supervision was awarded on 5th March 1986. The work physically commenced on 1st September 1986. The contractor was suspended in 1989 in order to allow Government investigation of the course of the failed sections of the road. The contract was eventually terminated. The project remains nearly 60% completed with UA 13.44 million disbursed. There have not been any disbursements since 9th March 1989. The Government has confirmed that the dispute between the Government and Messrs. ABU and Partners has been resolved with no legal or financial obligations to the Bank. On 18th December 1997, the Government requested Bank's approval to revise the list of works and services with a view to completing the project by utilizing the remaining UA 10.23 million. The Bank approved the Government's request on 19th April 1999, with the revised deadline for final disbursement being 31st December 2002. Since the approval of the revised list of works and services, the Government has entered into contract with a consulting firm for the design review, pre-tender activities and supervision of works. The draft tender documents are currently being reviewed by the Bank. However, the pre-qualifying contractors is completed. However, the Government has been very slow in implementing the project. ACTION: The Government should speed up the procurement process. The Bank's mission that is scheduled for early March will conclude the review of the tender Documents with the Government.

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data