In January 1999, China Light and Power Ltd. (CLP) had finalized the Guangdong Huaiji Hydro-electric Power Project, which involved a 30-year BOT contract to build, own and operate of 9 small scale power stations with a total installed capacity of 98 MW in Huaiji County in northwestern Guangdong Province.

The total cost of the project is US$115.7 million (HK$900 million). CLP owned 41.5% of the

Project Information FAQ

Project Information

4 Q
The project “Guangdong Huaiji Power” is an infrastructure initiative in the Hydro sector, located in China. Taiyo aggregates data on it from World Bank Group.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

active

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

In January 1999, China Light and Power Ltd. (CLP) had finalized the Guangdong Huaiji Hydro-electric Power Project, which involved a 30-year BOT contract to build, own and operate of 9 small scale power stations with a total installed capacity of 98 MW in Huaiji County in northwestern Guangdong Province. The total cost of the project is US$115.7 million (HK$900 million). CLP owned 41.5% of the scheme through subsidiary, CLP Hydro Power Ltd., while Sun Huang Kai China Development Fund Ltd., a subsidiary of Sun Huang Kai of Hong Kong,, owned 8.5%. The remaining 50% stake was held by Huaiji County Huilian Hydro-electric (group) Co., Ltd. The electricity that is generated was to be sold to the power grids of Huaiji and Guangdong Province. In June 2005, CLP completed the buy-out of Sun Hung Kai China Development Fund Limited's interest in Huajji. The government of Zhaoqing City in Guangdong had approved the restructuring of Huaiji's shareholding and CLP's interest in Huaiji increased to 75%. The Huaiji County Huilian Hydro-electric (Group) Co., Ltd. held the rest of 25%. The restructuring enabled CLP to exercise greater control over the project. Five of these power stations were commissioned between 1975 and 1996 while four new stations were completed at the end of 2001. The largest of the stations was the 36 MW Gaotang scheme while the smallest was the 1.5 MW Longzhongtan scheme. With all nine power stations completed, the Huaiji scheme was expected generate 390 GWH annually.

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data