Hai Long Offshore Wind Project
Sector: Wind • Location: Taiwan
Source: The Globe and Mail
The 1 gigawatt Hai Long offshore wind project in Taiwan. Fabrication of remaining major components has been completed, turbine installation resumed after April 1, 2026, with 51 of 73 turbines installed and 32 generating power. All cabling work is complete. The project remains on track for commercial operation in 2027.
- Status
- Under Construction
- Sector
- Wind, Power Generation (CCGT), Telecommunications, Manufacturing (Industrial), Commercial
- Location
- Taiwan
- Updated
- 22 Jul 2026
- Source
- The Globe and Mail
ConstructChat
Ask ConstructChat about Hai Long Offshore Wind Project
Pick a question to edit it, or write your own.
First answer free · no account
Project Information FAQ
Project Information
Participants
| Not available for this record. |
Status
Original status | under construction |
Taiyo status | Under Construction |
Taiyo last update | 2026-07-22 |
Contact
| Not available for this record. |
Description
Description | The 1 gigawatt Hai Long offshore wind project in Taiwan. Fabrication of remaining major components has been completed, turbine installation resumed after April 1, 2026, with 51 of 73 turbines installed and 32 generating power. All cabling work is complete. The project remains on track for commercial operation in 2027. |
Original sector | Energy |
Location
Country | Taiwan |
Source
Source | The Globe and Mail |
URL |
More Details
Record type | Project |
Sector | Wind, Power Generation (CCGT), Telecommunications, Manufacturing (Industrial), Commercial |
Article published date | 2026-05-19 |
Research
Free account
View all details
You are reading the public part. A free account opens the rest:
- Every detail on this project
- News and media coverage
- Technical research
Free account · no card · lands you back on this project