Implementation and Monitoring of Song Bung 4 Hydropower Project Resettlement and Ethnic Minority Development Plan

Sector: Road • Location: Vietnam

Source: Asian Development Bank (ADB)

Project
Closed

On 26 June 2008, the Asian Development Bank (ADB) approved Loan 2429-VIE: Song Bung 4 (SB 4) Hydropower Project for $196 million, which became effective on 16 January 2009. The Project consists of the construction of a 156-megawatt hydropower plant on the Song Bung in the Vu Gia-Thu Bon river basin and a 110-meter (m)-high roller compacted concrete dam on the same river with a crest length of 367

Project Information FAQ

Project Information

5 Q
The project “Implementation and Monitoring of Song Bung 4 Hydropower Project Resettlement and Ethnic Minority Development Plan” is an infrastructure initiative in the Road sector, located in Vietnam. Taiyo aggregates data on it from Asian Development Bank (ADB).

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

Closed

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

On 26 June 2008, the Asian Development Bank (ADB) approved Loan 2429-VIE: Song Bung 4 (SB 4) Hydropower Project for $196 million, which became effective on 16 January 2009. The Project consists of the construction of a 156-megawatt hydropower plant on the Song Bung in the Vu Gia-Thu Bon river basin and a 110-meter (m)-high roller compacted concrete dam on the same river with a crest length of 367 m. The Project is located in Nam Giang District of Quang Nam Province in Central Viet Nam, which is predominantly inhabited by indigenous people belonging to the Co Tu ethnic minority. The SB 4 Hydropower Project will result in the relocation of more than 1,200 Co Tu ethnic minority people in Zuoih commune in Nam Giang District. The resettlement cost is funded by the Electricity of Viet Nam (EVN). The Project is also supported by a complementary grant of $2 million financed by the Japan Fund for Poverty Reduction (JFPR) under Grant 9120: Livelihood Improvement of Vulnerable Ethnic Minority Communities Affected by the SB 4 Hydropower Project in Quang Nam Province. The JFPR project was approved by ADB on 26 June 2008 and became effective on 10 November 2008. The SB 4 Hydropower Project has several social impacts on the people who live in the reservoir, downstream, and upstream areas. The impacts include the (i) relocation of more than 1,200 people living in the reservoir area, which represents more than 97% of the people in the area, and 27,340 people from 89 villages along the Bung River downstream and upstream of the dam; and (ii) acquisition of land for more than 500 ethnic minority people for the development of resettlement sites and access roads to resettlement sites. In view of these, SB 4 Hydropower Project is considered a high-risk project.

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data