logo

Ind-Barath Energies Thoothukudi Limited (IBETL)

Sector: Biomass • Location: India

Source: World Bank Group

Project
Active

Ind-Barath Energies Thoothukudi Limited (IBETL) developed a 20.0 MW biomass coal based power plant at Thoothukudi, Tamil Nadu. IBETL was owned by Ind-Barath Power Infra Private Ltd. (72.3%). The power plant was commissioned in June 2006. Power was sold to PTC India on merchant basis. Pursuant to an agreement dated April 9, 2009, as amended on October 22, 2009, IBETL sells 15.0 MW of power per mont

Status
Prospective
Sector
Biomass, Power Generation (CCGT), Government
Location
India
Updated
22 Jul 2026
Source
World Bank Group

ConstructChat

Ask ConstructChat about Ind-Barath Energies Thoothukudi Limited (IBETL)

Pick a question to edit it, or write your own.

First answer free · no account

I am a

Project Information FAQ

Project Information

5 Q
The project “Ind-Barath Energies Thoothukudi Limited (IBETL)” is an infrastructure initiative in the Biomass sector, located in India. Taiyo aggregates data on it from World Bank Group.

Participants

Sponsoring Agency

Company

Status

Original status

Active

Taiyo status

Prospective

Taiyo last update

2026-07-22

Contact

Not available for this record.

Description

Description

Ind-Barath Energies Thoothukudi Limited (IBETL) developed a 20.0 MW biomass coal based power plant at Thoothukudi, Tamil Nadu. IBETL was owned by Ind-Barath Power Infra Private Ltd. (72.3%). The power plant was commissioned in June 2006. Power was sold to PTC India on merchant basis. Pursuant to an agreement dated April 9, 2009, as amended on October 22, 2009, IBETL sells 15.0 MW of power per month to PTC India at an average tariff rate of Rs. 5.90 per kWh. The agreement is valid until March 31, 2014, however the tariff is valid until May 31, 2010, after which it is subject to renegotiation. The project was registered under the United Nations Framework Convention on Climate Change (“UNFCCC”) and hence is eligible for generating and selling CERs under the Kyoto Protocol’s Clean Development Mechanism (“CDM”) project. The project cost was estimated to be Rs 660 million (US$15 million). Financial closure was achieved in 2005. The IBETL Power Project was funded through a combination of equity contributions from our Company and other investors, and secured and unsecured debt. As of March 31, 2010, the total equity investment in IBETL is Rs. 156.59 million. Financing secured amounted to Rs. 503.40 million for the implementation of the IBETL Power Project, from three lenders, including Indian Renewable Energy Development Agency Limited, Andhra Bank and UCO Bank. As of March 31, 2010, Rs. 330.31 million and Rs. 347.81 million in principal amount of secured and unsecured loans, respectively, remains outstanding.

Original sector

Energy

Budget

Location

Country

India

Source

Source

World Bank Group

URL

More Details

Record type

Project

Sector

Biomass, Power Generation (CCGT), Government

Article published date

2024-09-23

More on this project

Research

Free account

View all details

You are reading the public part. A free account opens the rest:

  • Every detail on this project
  • News and media coverage
  • Technical research
View all details

Free account · no card · lands you back on this project