In June 2008, CTEEP was awarded in a competitive bidding process the contract to build and operate 150-km of transmission line and two substations located in the states of Parana, Santa Catarina and Rio Grande do Sul. Besides CTEEP, twelve other companies took part in the contest: Spanish company Cobra Instalaciones y Servicios; state-owned Eletrosul; Brazilian Triunfo Participações; Schahin Enge

Project Information FAQ

Project Information

4 Q
The project “Interligacao Eletrica Sul” is an infrastructure initiative in the Power Generation (CCGT) sector, located in Brazil. Taiyo aggregates data on it from World Bank Group.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

active

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

In June 2008, CTEEP was awarded in a competitive bidding process the contract to build and operate 150-km of transmission line and two substations located in the states of Parana, Santa Catarina and Rio Grande do Sul. Besides CTEEP, twelve other companies took part in the contest: Spanish company Cobra Instalaciones y Servicios; state-owned Eletrosul; Brazilian Triunfo Participações; Schahin Engenharia; Spanish Cymi Holding; Terna Participacoes; Orteng Equipamentos e Sistemas; state-owned Copel Geracao e Transmissao; TBE Brasil; Alupar; Spanish Abengoa; and Elecnor Transmissao de Energia. The bidding criteria set by the regulatory agency ANEEL was the lowest required annual revenue. CTEEP presented the lowest offer, a total value of US$ 3.6 million (BRL 6.6 million), 0.5% the ceiling set by the regulatory agency. The contract was signed in October 2008, and the sponsors created the company Interligacao Eletrica Sul to lead the project during the 30-year contract period. In August 2009, the shareholding structure was modified as follows: CTEEP (50.1%) and the Spanish company Cymi Holding S.A., a subsidiary of ACS Group (49.9%). The sponsor committed to invest US$ 20.1 million (BRL 36.8 million) in the transmission line. The construction works commenced in November 2008, but financial closure was only achieved in December 2010, when the sponsor was granted a US$ 10.28 million (BRL 18.1 million) loan from BNDES. The remaining cost was set to be financed with the sponsors’ internal resources. Construction works were expected to be concluded in 2011.

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data