L&T Vadodara-Bharuch Tollway Limited

Sector: Road • Location: India

Source: World Bank Group

Project
Active

In July 2006, National Highways Authority of India (NHAI) awarded a 15 year concession contract to India’s Larsen and Toubro Limited (L&T) to widen and strengthen the 83 Km stretch on National Highway 8 (NH-8), between Vadodara and Bharuch, in Gujarat State. Under the contract, L&T was responsible for the operation, maintenance and widening of the existing four-lane road to a six lane divided high

Project Information FAQ

Project Information

4 Q
The project “L&T Vadodara-Bharuch Tollway Limited” is an infrastructure initiative in the Road sector, located in India. Taiyo aggregates data on it from World Bank Group.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

active

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

In July 2006, National Highways Authority of India (NHAI) awarded a 15 year concession contract to India’s Larsen and Toubro Limited (L&T) to widen and strengthen the 83 Km stretch on National Highway 8 (NH-8), between Vadodara and Bharuch, in Gujarat State. Under the contract, L&T was responsible for the operation, maintenance and widening of the existing four-lane road to a six lane divided highway. In addition, the project included 10 major and 36 minor bridges, 11 flyovers, two road over bridges, 11km of service roads, and pedestrian and cattle crossings at specified locations. The 15 year concession term included the construction period of 30 months. The Vadodara-Bharuch road project, awarded under National Highway Development Project – Phase V, forms an important link in the high density corridor connecting Mumbai and Delhi. The road expansion was expected to ease traffic congestion and give significant stimulus to trade and commerce in the entire region. L&T established a special purpose vehicle, L&T Vadodara-Bharuch Tollway Limited, to implement the project. L&T won the international competitive tender, conducted by NHAI, by offering to make an upfront payment of US$ 104 million for the right to collect tolls during the term of the concession. According to the tender documents, NHAI would pay up to 40 percent of the capital costs as grant to the concessionaire, subject to competitive bidding. However, in high traffic density corridors like this one that are very profitable, the bidders usually offered an upfront payment to NHAI instead of seeking a grant. The total capital cost of the project was estimated at US$ 145.6 million. The project reached financial closure in December 2006. State Bank of India was the lead arranger of the bank debt, which had a 13.5 year tenor and featured cash sweeps with accelerated payments. Construction work on the project began in Jan 2007 and was expected to be completed by July 2009. As per NHAI, the project was completed in September 2009.

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data