In January 2015, CPFL Geracao de Energia S/A., a subsidiary of the Chinese company State Grid, was awarded the contract to build and operate the 1-km transmission line and the Morro Agudo substation, located at the state of Sao Paulo (500 kV in capacity).

Besides CPFL, another bidder took part in the contest: Abengoa Construcao Brasil Ltda. The bidding criteria set by the regulatory agency ANEEL

Status
Prospective
Sector
Steel, Power Generation (CCGT), Government, Manufacturing (Industrial), Commercial
Location
Brazil
Updated
22 Jul 2026
Source
World Bank Group

ConstructChat

Ask ConstructChat about Morro Agudo Substation

Pick a question to edit it, or write your own.

First answer free · no account

I am a

Project Information FAQ

Project Information

5 Q
The project “Morro Agudo Substation” is an infrastructure initiative in the Steel sector, located in Brazil. Taiyo aggregates data on it from World Bank Group.

Participants

Sponsoring Agency

Status

Original status

Active

Taiyo status

Prospective

Taiyo last update

2026-07-22

Contact

Not available for this record.

Description

Description

In January 2015, CPFL Geracao de Energia S/A., a subsidiary of the Chinese company State Grid, was awarded the contract to build and operate the 1-km transmission line and the Morro Agudo substation, located at the state of Sao Paulo (500 kV in capacity). Besides CPFL, another bidder took part in the contest: Abengoa Construcao Brasil Ltda. The bidding criteria set by the regulatory agency ANEEL was the lowest required annual revenue. CPFL presented the lowest offer, a total value of US$ 3.2 million (BRL 10.836 million), 32.59% below the ceiling set by the regulatory agency. The contract was signed in March 2015, and the sponsors created the company CPFL Transmissao Morro Agudo S.A. to lead the project during the 30-year contract period. The sponsor committed to invest US$ 31.1 million (BRL 107.3 million) in the project. Construction works commenced in August 2016 and were in its final stages by June 2017. Financing information was not available. The company was granted the right to take part in the government program called Regime Especial de Incentivos para o Desenvolvimento da Infra-Estrutura (Reidi). Companies selected to take part in this program were given tax cuts in the acquisition of capital equipment and construction material acquired both in the domestic and international markets (this incentive represented a cost reduction of about 9.25%). In addition, the company was allowed to use accelerated depreciation methods of accounting for construction expenditures.

Original sector

Energy

Budget

Location

Country

Brazil

Source

Source

World Bank Group

URL

More Details

Record type

Project

Sector

Steel, Power Generation (CCGT), Government, Manufacturing (Industrial), Commercial

Article published date

2024-09-19

More on this project

Research

Free account

View all details

You are reading the public part. A free account opens the rest:

  • Every detail on this project
  • News and media coverage
  • Technical research
View all details

Free account · no card · lands you back on this project