Nebraska Medicine contracted the Design-Build team of Kiewit Building Group and Leo A Daly to design and build a new seven-level, 735-stall parking garage on the footprint of the existing surface of Parking Lot 6. The team was given 14 months to design and construct the project. The new Parking Lot 6 garage is rectangular (325 ft long x 116 ft wide), and uses a double-helix ramp system with one-wa

Project Information FAQ

Project Information

5 Q
The project “Nebraska Medicine Lot 6 Parking Structure” is an infrastructure initiative in the Automotive sector, located in United States of America (USA). Taiyo aggregates data on it from Kiewit Construction.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

completed

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

Nebraska Medicine contracted the Design-Build team of Kiewit Building Group and Leo A Daly to design and build a new seven-level, 735-stall parking garage on the footprint of the existing surface of Parking Lot 6. The team was given 14 months to design and construct the project. The new Parking Lot 6 garage is rectangular (325 ft long x 116 ft wide), and uses a double-helix ramp system with one-way traffic and crossover locations where sloping decks intersect, which was deemed the most efficient method of moving cars in and out of the structure during peak times for staff. There are two elevators in the south tower to access each level, and a pedestrian bridge connects the Parking Lot 6 garage to the older Parking Lot 5 garage. Significant weather delays hampered progress on the project, however expert project management and innovative use of 3D modeling ultimately streamlined the job schedule and allowed the project to be completed well under budget.

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data