Paka Power Plant

Sector: Power Generation (CCGT) • Location: Malaysia

Source: World Bank Group

Project
Active

Two power plants were developed by YTL Power Generation Sdn Bhd that had a combined capacity of 1212-MW, or 808-MW (2x390-MW) at Paka and 404-MW (1x390-MW) at Pasir, respectively. IPP licenses for both plants were granted in April 1993 with construction beginning later that year. The plants went into service in 1994.

The joint venture company, YTL Power Generation Bhd Sdn., was intially owned

Project Information FAQ

Project Information

4 Q
The project “Paka Power Plant” is an infrastructure initiative in the Power Generation (CCGT) sector, located in Malaysia. Taiyo aggregates data on it from World Bank Group.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

active

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

Two power plants were developed by YTL Power Generation Sdn Bhd that had a combined capacity of 1212-MW, or 808-MW (2x390-MW) at Paka and 404-MW (1x390-MW) at Pasir, respectively. IPP licenses for both plants were granted in April 1993 with construction beginning later that year. The plants went into service in 1994. The joint venture company, YTL Power Generation Bhd Sdn., was intially owned by YTL International Sdn Bhd (59.56%), Tenaga Nasional Bhd (4.4%), Employees Provident Fund (EPF)(5.9%), Bara Ak Tif (5.39%), Mayban Ventures Sdn Bhd (2.71%), JL Investment Singapore Private Ltd. (0.59%), a unit of John Laing PLC., and local shareholders (18.72%). The state-controlled Tenaga Nasional Bhd. relinquished its 4.4% stake by selling 71 million shares in December 2003 to YTL Power, and in March 2004 it sold 19.7 million more shares to EPF. Project costs were US$836.0 million for Paka and US$416 million for Pasir Gudang., or a total cost of M$2.66 billion in local currency. M$1.5 billion was raised via bond subscription with the Employment Provident Fund (EPF) and M$1.16 billion was raised via a syndicated bank loan. A 21-year power-purchase-agreement with Tenaga (TNB) that includes fuel pass through provisions was signed in March 1993. A fuel supply agreement with Petronas was also signed in March 1993. In Feb. 2000, YTL issued US$197.4 million fixed-rate bond (deal led by Deutsche Bank). None None

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data