The government in January 1999 awarded to Red Electrica del Sur the 32-year concession to build and operate three 220-kV transmission lines in southern Peru. Red Electrica must strengthen the second circuit of the 220 kW Socabaya Moquegua power line and balance the Maquegua-Puno and Moquegua-Tacna lines so they can be intergrated in the same circuit.

Red Electrica del Dur is a consortium compr

Project Information FAQ

Project Information

4 Q
The project “Red Electrica del Sur” is an infrastructure initiative in the Power Generation (CCGT) sector, located in Peru. Taiyo aggregates data on it from World Bank Group.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

active

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

The government in January 1999 awarded to Red Electrica del Sur the 32-year concession to build and operate three 220-kV transmission lines in southern Peru. Red Electrica must strengthen the second circuit of the 220 kW Socabaya Moquegua power line and balance the Maquegua-Puno and Moquegua-Tacna lines so they can be intergrated in the same circuit. Red Electrica del Dur is a consortium comprised of Red Electrica de Espana (25 percent), Cobra Peru (20 percent), Abengoa Peru (20 percent), Banco Hispano Americano (15 percent) and Peruvian government investment agency Proinversion (15 percent). In 2004 the Peruvian government announced the release of their 15 percent share - a bid of US$5.35 million was set forth by investment fund AC Capitales. The investment fund was formed by three pension funds: Integra, Profuturo, and Horizonte. Clearance of the sell was not expected until early 2005. Redesur will invest nearly $75-million to set up a 445-km transmission line over 42 months. By February 2000, the first phase was expected to start operations between Arequipa and Moquegua by which time the 32-year duration of the concession will commence. This contract includes a period of two years for the construction of 444 km of 220 kV lines and four substations. In Dec. 2000, the IADB approved a US$ 53 million financing package to finance the construction works. The sell of 15% stake of the govenment in the company in Dec 2004 needs to be added. See electronic filing system. None

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data