Region Oil was planning the development of the 400 MW Xekong 5 hydropower plant, near Sekong. The project capacity was reported as 330 MW by the government of Laos.

The MOU for the project was signed in 2005 and expired in April 2009. The PDA was signed in June 2009 and the feasibility study submitted in June 2009. The environmental and social impact assessments were done by Norconsult AS from No

Project Information FAQ

Project Information

5 Q
The project “Region Oil Xekong V HPP” is an infrastructure initiative in the Water Supply and Storage sector, located in Lao PDR. Taiyo aggregates data on it from World Bank Group.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

Active

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

Region Oil was planning the development of the 400 MW Xekong 5 hydropower plant, near Sekong. The project capacity was reported as 330 MW by the government of Laos. The MOU for the project was signed in 2005 and expired in April 2009. The PDA was signed in June 2009 and the feasibility study submitted in June 2009. The environmental and social impact assessments were done by Norconsult AS from Noway and National Consulting Company from Laos. The output was partially to be exported to Thailand. The concession agreements and PPA were reported as under negotation by the Laos government. No further financial details were available as of December 2011. http://www.poweringprogress.org/download/News/news_criping/Lao%20Media/Vientiane%20Times/2008/august/VientianeTimes_14thAug2008_Xekhaman3_construction_costs_rise.pdf http://laovoices.com/three-xekong-river-dams-move-closer-to-reality/ Three Xekong River dams move closer to reality Posted by LV on Thursday, December 15, 2011 · 1 Comment Region Oil Company of Russia is working on the formation of a project company in Laos to build three dams in Xekong and Attapeu provinces. The planned hydropower projects are named the Xekong 4, Xekong 5 and Nam Kong 1, all on the Xekong River. “Region Oil intends to form a project company next year,” the company’s Deputy General Director Mr Vasily M. Morgun said recently. The project company would sign a tariff memorandum of understanding (MOU) with the Electricity Generating Authority of Thailand (EGAT). “The most important part of the process is to sign a concession agreement with the Lao government, which will pave the way for the start of construction,” he said. Mr Morgun said a draft concession agreement has been submitted to the Ministry of Energy and Mines for consideration. Region Oil signed an MOU on the three hydropower plants in 2007 and set up representative offices in Xekong and Attapeu provinces. The company says it works within the laws of Laos and in line with the Project Development Agreements signed with the Lao government. The dams will cost about 16 trillion kip (US$2 billion) to build and will have an installed capacity of about 1,200 megawatts. Last year the Lao government approved the Lao Holding State Enterprise to represent the interests of the government and own shares in the project company, according to a company report. Korea Western Power Co., Ltd. (KOWEPO) of the Republic of Korea also expressed interest in taking part in the development of the three dams. KOWEPO has been studying the project documents and its staff have visited the project sites. Region Oil and Electricite du Laos (EDL) signed an MOU on tariffs last year, under which 10 percent of electricity generated by the dams will be supplied to EDL for domestic supply. The schedules relating to social and environmental obligations have been completed for the Xekong 4 and Nam Kong 1 dams and submitted to the Ministry of Natural Resources and Environment for consideration. Unexploded ordnance has been cleared around the Xekong 4 dam site on an area of 777.2 hectares, as well as on an area of 42 hectares where an access road is planned. Unexploded ordnance has also been cleared around the Nam Kong 1 dam site on 91.2 hectares and on 55.3 hectares where an access road will be built. Comprehensive research on the geography, geology, hydrology and meteorology of the area has been completed for the purposes of project design. An environmental management plan, resettlement action plan, and social action plan for the three proposed dams have already been drawn up and approved by the Lao government. Source: Vientiane Times

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data