Samudera Palaran Terminal

Source: World Bank Group

Project
Active

The project was awarded in July 2007 by direct negotiation, when PT Pelabuhan Samudera Palaran (PSP) entered into a joint operation agreement with the Samarinda city goverment under a BOT contract for 50 years.

Under the term of the agreement, PT Pelabuhan Samudera Palaran (PSP) was to make an investment of US$60 million (IDR550 billion) to bring capacity to 220,000 TEUs per year.

In March

Project Information FAQ

Project Information

5 Q
The project "Samudera Palaran Terminal" is an infrastructure initiative in the Government, Water Supply and Storage, Seaport, Commercial sector, located in N/A, Indonesia. Taiyo aggregates data from World Bank Group, including information on sponsoring government bodies, EPCs, and contractors.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

Active

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

The project was awarded in July 2007 by direct negotiation, when PT Pelabuhan Samudera Palaran (PSP) entered into a joint operation agreement with the Samarinda city goverment under a BOT contract for 50 years. Under the term of the agreement, PT Pelabuhan Samudera Palaran (PSP) was to make an investment of US$60 million (IDR550 billion) to bring capacity to 220,000 TEUs per year. In March 2009, the 50-year BOT Samudera Palaran Container Terminal project reached closure. This project was developed by PT Pelabuhan Samudera Palaran (PSP), a joint-venture between privately-owned PT Samudera Indonesia Tbk (75%) and state-owned PT Pelabuhan (Pelindo) IV (25%). Construction of the terminal began in June 2008 and was 43% complete as of March 2009. The project was expected to be operational in December 2009. The detailed information on financing of the project was not available. The container terminal was completed in May 2010.

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data