logo

Serra da Mesa Transmissora de Energia

Sector: Power Generation (CCGT) • Location: Brazil

Source: World Bank Group

Project
Active

In November 2005, Isolux SA, was awarded in a competitive bidding process organized by the regulatory agency ANEEL the contract to build and operate a 675 km transmission line and two substations located in the states of Minas Gerais, Goias and Distrito Federal (Serra da Mesa 2 – Luziania, Luziania – Samanbaia, Luziania – Paracatu 4 – Emborcacao). Besides Isolux SA, eight other companies took part

Project Information FAQ

Project Information

4 Q
The project “Serra da Mesa Transmissora de Energia” is an infrastructure initiative in the Power Generation (CCGT) sector, located in Brazil. Taiyo aggregates data on it from World Bank Group.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

active

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

In November 2005, Isolux SA, was awarded in a competitive bidding process organized by the regulatory agency ANEEL the contract to build and operate a 675 km transmission line and two substations located in the states of Minas Gerais, Goias and Distrito Federal (Serra da Mesa 2 – Luziania, Luziania – Samanbaia, Luziania – Paracatu 4 – Emborcacao). Besides Isolux SA, eight other companies took part in the contest: COBRA INSTALACIONES Y SERVICIOS S.A., CONSORCIO LUZIANIA, TRANSMISSORA SUDESTE NORDESTE S.A. - TSN, ABENGOA S.A., NEOENERGIA, CONSÓRCIO BANDEIRANTE, ISA - INTERCONEXION ELECTRICA S.A. E.S.P., and ELECNOR S.A. The bidding criteria set by ANEEL was the lowest required annual revenue. Isolux SA presented the lowest offer, a total value of US$ 27.5 million (BRL 66.9 million), 42.6% below the ceiling set by the regulatory agency. The contract was signed in May 2006, and the sponsors created the company Serra da Mesa Transmissora de Energia to lead the project during the 30-year contract period. The sponsor committed to invest US$ 229.5 million (BRL 420 million) in the transmission line. The environmental licence was granted in January 2007 and the operation of the transmission line started in April 2008. In 2008, MIGA issued a guarantee of € 20.9 million ($33 million equivalent) to Cobra Instalaciones y Servicios S.A. of Spain to cover its equity investment in the Serra da Mesa Transmissora de Energia project in Brazil. The coverage was agreed for a period of up to 15 years against the risks of transfer restriction and breach of contract. In March 2010, the shareholding structure was modified when a Chinese state – owned company, SGID, acquired Serra Paracatu Transmissora de Energia and other transmission projects from Plena Transmissora de Energia (Isolux, 33,3%; Elecnor, 33,3%; Cobra Instalaciones y Servicios, 33,3%), which held 100% of the shares of the project company at the time the transaction took place. SGID invested US$ 1.72 billion (BRL 3.1 billion) in the acquisition of Plena Transmissora de Energia.

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data