Solar Array and Battery Construction Schedule

Sector: Car parking • Location: California, United States of America

Source: Sonoma State University

Project

Tuesday, May 2, 2023, 1:00pm TO: Campus Community FR: J. Dana Twedell, Associate Vice President, Facilities Management

The construction for the university's solar and battery project will begin May 22 and continue through November 6. This project will benefit our campus with 4.5 megawatts of renewable solar energy, as well as 1.5 megawatts of battery energy storage capacity. It is estimated tha

Project Information FAQ

Project Information

3 Q
The project “Solar Array and Battery Construction Schedule” is an infrastructure initiative in the Car parking sector, located in California, United States of America. Taiyo aggregates data on it from Sonoma State University.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

Obfuscated Data

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

Tuesday, May 2, 2023, 1:00pm TO: Campus Community FR: J. Dana Twedell, Associate Vice President, Facilities Management The construction for the university's solar and battery project will begin May 22 and continue through November 6. This project will benefit our campus with 4.5 megawatts of renewable solar energy, as well as 1.5 megawatts of battery energy storage capacity. It is estimated that the university will save $6 million in utility costs over the next 30 years. There will be a groundbreaking ceremony on May 10 at 9 a.m. at Parking Lot J. The campus community is invited to attend. Construction will be in phases, beginning with parking lots E and F, followed by Lot J, then Lot R6, and finally with Lot R7. The map below shows the locations of the solar panels in each of the parking lots. Solar Array Parking Lot Map.jpg A map of the parking lots in which a solar array project is taking place Construction Schedule Parking Lot E & F May 22 - August 4 Parking Lot J August 7 - September 15 Parking Lot R6 September 18 - October 27 Parking Lot R7 September 25 - November 6 During each phase of construction, the parking lot will be fenced off and restricted from access. Sufficient parking will be available in the adjacent parking lots during each construction phase. We are excited to begin the construction of this renewable and sustainable solar energy project. We understand this will impact the campus, specifically available parking. Thank you in advance for your support and patience as we create a more sustainable SSU. If you have any questions, please contact Dana Twedell at twedell@sonoma.edu.

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data