Tarlac- la Union Toll Expressway (TPLEX) - Phase 1

Sector: Road • Location: Philippines

Source: World Bank Group

Project
Active

In July 2011, Private Infra Dev Corp. (PIDC) secured financing for the 88.15km Tarlac-Pangasinan-La Union Toll Expressway (TPLEX) between Baguio City and Manila to be developed under a build-own-transfer contract. The TPLEX was to be developed in two phases: Phase I would entail a 2-lane express way between Tarlac to Rosario, La Union and Phase II would cover the widening of the road to 4 lanes

Project Information FAQ

Project Information

5 Q
The project “Tarlac- la Union Toll Expressway (TPLEX) - Phase 1” is an infrastructure initiative in the Road sector, located in Philippines. Taiyo aggregates data on it from World Bank Group.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

active

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

In July 2011, Private Infra Dev Corp. (PIDC) secured financing for the 88.15km Tarlac-Pangasinan-La Union Toll Expressway (TPLEX) between Baguio City and Manila to be developed under a build-own-transfer contract. The TPLEX was to be developed in two phases: Phase I would entail a 2-lane express way between Tarlac to Rosario, La Union and Phase II would cover the widening of the road to 4 lanes when Phase II would reach 25,000 vehicles per day. The estimated project cost was US$290 million. Government support amounts to US83.8 million (right-of-way worth P793million; and a cash subsidy of P2.9billion) Financing, secured in July 14, 2011, comprises of a 10-year credit facility of US$267.44 million (P11.5 billion) arranged by Banco de Oro Unibank. The bidding for this project took place in November 2007, and PIDC was issued a notice of award in February 2008. The notices to proceed with the construction of phase I (in the sections were ROW was secured) were issued in in July 2010, Novemeber 2010 and January 2011. The road was expected to be operational in 2016. As of October 2012, section one was 68.95% complete. capital grants = value of right of way

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data