Uzbekistan: Karakalpakstan and Khorezm Local Roads Network Reconstruction Project

Sector: Water Supply and Storage • Location: Uzbekistan

Source: Asian Infrastructure Investment Bank (AIIB)

Project
Approved

The Karakalpakstan and Khorezm Local Roads Network Reconstruction Project (the Project) aims to rehabilitate and reconstruct up to 516.1 kilometers (km) of local roads across 23 districts in the Republic of Karakalpakstan and the Khorezm Region of Uzbekistan. These roads serve as critical links between rural communities and key socioeconomic services such as markets, schools, hospitals, and admini

Project Information FAQ

Project Information

5 Q
The project “Uzbekistan: Karakalpakstan and Khorezm Local Roads Network Reconstruction Project” is an infrastructure initiative in the Water Supply and Storage sector, located in Uzbekistan. Taiyo aggregates data on it from Asian Infrastructure Investment Bank (AIIB).

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

approved

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

The Karakalpakstan and Khorezm Local Roads Network Reconstruction Project (the Project) aims to rehabilitate and reconstruct up to 516.1 kilometers (km) of local roads across 23 districts in the Republic of Karakalpakstan and the Khorezm Region of Uzbekistan. These roads serve as critical links between rural communities and key socioeconomic services such as markets, schools, hospitals, and administrative centers. The Project will finance the following activities: civil works for the rehabilitation of up to 516.1 km of rural roads using climate-resilient pavement structures and improved safety features; consultancy services for construction supervision and quality control; development of a digital geospatial platform to support construction monitoring, grievance management, and climate vulnerability mapping; and institutional strengthening and capacity building, including targeted programs to promote women and youth empowerment. Project implementation will be carried out over 5 years through two phases, 1 and 2. The financing for the Project is proposed to be committed via two separate loan tranches, each with its own Loan agreement, in line with the Project's implementation readiness and allowing for operational viability and efficient resource allocation. Phase 1: Reconstruction of up to 188 km of local roads across 9 districts in Khorezm Region, together with Institutional Strengthening and Capacity Building as well as Development of Digital Geospatial Platform and Women and Youth Empowerment Program with a proposed AIIB financing amount of USD71.163 million. Phase 2: Reconstruction of up to 328.1 km of local roads across 14 districts in the Republic of Karakalpakstan, with an expected AIIB financing amount of USD102.312 million. This Phase will be prepared and submitted for AIIB management's verification once agreed conditions for Tranche 2 readiness are met. The Project complements the Government of Uzbekistan's efforts to improve regional and local road infrastructure, supporting more inclusive and balanced development alongside existing investments in national and international corridors. Local roads in Uzbekistan, many built in the 1950s-60s, have suffered from decades of underinvestment, resulting in widespread deterioration and limited accessibility. Improving these roads is critical to unlocking the industrial and agricultural potential of underserved areas, particularly in Western Uzbekistan, including the environmentally fragile Aral Sea region. Reconstruction works will include full pavement rehabilitation, bridge repairs and new small-scale structures, enhanced drainage, safety signage, and bus stops. Where needed, sidewalks will be added to improve pedestrian safety, especially near schools and community centers. All civil works are planned within the existing rights-of-way, minimizing the need for land acquisition or resettlement. Environmental impacts are expected to be minor and localized to construction activities. The Project also includes a dedicated inclusion component, designed to enhance economic participation and resilience in project-affected communities. This includes vocational training for women, road safety and climate awareness campaigns for youth, and targeted support for women's entrepreneurship initiatives. These activities will be integrated with the development of the digital geospatial platform to facilitate inclusive monitoring, evidence-based planning, and transparent grievance redress.

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data