Wastewater Treatment Plant Electrical Transformer Replacement
The status, timeline and source of this project. A free account opens every field.
Source: Infrastructure Canada
Replace two existing main electrical transformers at the City’s wastewater treatment plant. Scope of work includes a detailed electrical needs assessment, pre-design, design, pre purchase of equipment (due to long lead times), design of the associated works inclusive of poles, overhead and underground cable, transfers, connections etc., purchase and installation of equipment. The assessment and pr
- Status
- Closed
- Sector
- Water Supply and Storage, Power Transmission, Power Generation (CCGT), Government
- Location
- Ontario, Canada
- Updated
- 22 Jul 2026
- Source
- Infrastructure Canada
ConstructChat
Ask ConstructChat about Wastewater Treatment Plant Electrical Transformer Replacement
Pick a question to edit it, or write your own.
First answer free · no account
Project Information FAQ
Project Information
Participants
Sponsoring Agency |
Status
Original status | completed |
Taiyo status | Closed |
Taiyo last update | 2026-07-22 |
Contact
| Not available for this record. |
Description
Description | Replace two existing main electrical transformers at the City’s wastewater treatment plant. Scope of work includes a detailed electrical needs assessment, pre-design, design, pre purchase of equipment (due to long lead times), design of the associated works inclusive of poles, overhead and underground cable, transfers, connections etc., purchase and installation of equipment. The assessment and pre-design work will confirm final electrical requirements, utility coordination with Brantford Power and costing. Both transformers are 1000kVA/27.6/4.16kV delta, primary metered units which provide all of the electrical service required to run the plant. These units are of undetermined age although field observations suggest that they are well over 20 years old. Routine maintenance and inspections indicate that both transformers have far exceeded their service lives and should be replaced to reduce the risk of complete failure, potential disruption to the operation of the plant and potential regulatory compliance issues. The existing transformers are also limiting required process improvements as they cannot handle any increased electrical load. The wastewater treatment plant is the only treatment facility in the City and services approximately 94,000 residents plus businesses. In the event that both transformers fail there is limited back-up capacity through diesel generators and could therefore either pose serious risk to the environment (Grand River receiving body) and potentially homes in the southern most part of the City. |
Original sector | Drinking Water and Wastewater |
Budget |
Location
Country | Canada |
State | Ontario |
Source
Source | Infrastructure Canada |
URL |
More Details
Record type | Project |
Sector | Water Supply and Storage, Power Transmission, Power Generation (CCGT), Government |
Article published date | 2025-06-04 |
Research
Free account
View all details
You are reading the public part. A free account opens the rest:
- Every detail on this project
- News and media coverage
- Technical research
Free account · no card · lands you back on this project