Wastewater Treatment Plant Electrical Transformer Replacement

Sector: Water Supply and Storage • Location: Ontario, Canada

Source: Infrastructure Canada

Project
Completed

Replace two existing main electrical transformers at the City’s wastewater treatment plant. Scope of work includes a detailed electrical needs assessment, pre-design, design, pre purchase of equipment (due to long lead times), design of the associated works inclusive of poles, overhead and underground cable, transfers, connections etc., purchase and installation of equipment. The assessment and pr

Project Information FAQ

Project Information

5 Q
The project “Wastewater Treatment Plant Electrical Transformer Replacement” is an infrastructure initiative in the Water Supply and Storage sector, located in Ontario, Canada. Taiyo aggregates data on it from Infrastructure Canada.

Want to explore the full details? View the full report

Participants

Sponsoring Agency

Obfuscated Data

Company

Obfuscated Data

Status

Original status

completed

Taiyo status

Obfuscated Data

Taiyo last update

00-00-0000

Available timestamps

00-00-0000

Available timestamp type

Obfuscated Data

Contact

Contact name

Obfuscated Data

Phone

0000000000

Email

ObfuscatedData@email.com

Address

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Description

Description

Replace two existing main electrical transformers at the City’s wastewater treatment plant. Scope of work includes a detailed electrical needs assessment, pre-design, design, pre purchase of equipment (due to long lead times), design of the associated works inclusive of poles, overhead and underground cable, transfers, connections etc., purchase and installation of equipment. The assessment and pre-design work will confirm final electrical requirements, utility coordination with Brantford Power and costing. Both transformers are 1000kVA/27.6/4.16kV delta, primary metered units which provide all of the electrical service required to run the plant. These units are of undetermined age although field observations suggest that they are well over 20 years old. Routine maintenance and inspections indicate that both transformers have far exceeded their service lives and should be replaced to reduce the risk of complete failure, potential disruption to the operation of the plant and potential regulatory compliance issues. The existing transformers are also limiting required process improvements as they cannot handle any increased electrical load. The wastewater treatment plant is the only treatment facility in the City and services approximately 94,000 residents plus businesses. In the event that both transformers fail there is limited back-up capacity through diesel generators and could therefore either pose serious risk to the environment (Grand River receiving body) and potentially homes in the southern most part of the City.

Original sub-sector

Obfuscated

Original Currency

USD

Original budget

000000000000000

Procurement method

Obfuscated Data

Budget

000000000000000

Location

Region

Obfuscated

Country

Obfuscated

State

Obfuscated Data

County

Obfuscated

Location

Obfuscated Data, Obfuscated data, obfuscated data, Obfuscated data

Source

Source reliability

High

Data quality score

100%

Source

Obfuscated Data

URL

obfuscated_data,obfuscateddata.com

More Details

Project Type

Obfuscated Data

Article Published Date

Obfuscated Data