Works contracts – Section 3 Paraćin – Trupale (design and build) for Railway Line under the Belgrade – Niš Railway Modernisation Project

The scope, dates and status of this tender. A free account opens every field.

Source: TED Europa

Tender
Prior Information Notice

The Works Contract covers Section 3 of the Belgrade–Niš Modernisation Project, which is divided into three subsections, (sub-section 3.2 Stalać – Đunis is already contracted). The works relate to Sub-sections 3.1 Paraćin–Stalać and 3.3 Đunis–Trupale. Sub-section Paraćin–Stalać is 20.8 km long, while Sub-section Đunis–Trupale is 37.7 km long. A total of nine stations will be reconstructed and mode

Status
Prospective
Sector
Power Generation (CCGT), Mass Transit, Rail, Tunnel, Road
Location
Serbia
Updated
3 Nov 2026
Source
TED Europa

ConstructChat

Ask ConstructChat about Works contracts – Section 3 Paraćin – Trupale (design and build) for Railway Line under the Belgrade – Niš Railway Modernisation Project

Pick a question to edit it, or write your own.

First answer free · no account

I am a

Tender Information FAQ

Tender Information

3 Q
The tender “Works contracts – Section 3 Paraćin – Trupale (design and build) for Railway Line under the Belgrade – Niš Railway Modernisation Project” is a tender record in Taiyo, linked to the Power Generation (CCGT) sector. It is issued for works, goods, or services related to Serbia.

Participants

Not available for this record.

Status

Original status

prior information notice

Taiyo status

Prospective

Taiyo last update

2026-11-03

Contact

Not available for this record.

Description

Description

The Works Contract covers Section 3 of the Belgrade–Niš Modernisation Project, which is divided into three subsections, (sub-section 3.2 Stalać – Đunis is already contracted). The works relate to Sub-sections 3.1 Paraćin–Stalać and 3.3 Đunis–Trupale. Sub-section Paraćin–Stalać is 20.8 km long, while Sub-section Đunis–Trupale is 37.7 km long. A total of nine stations will be reconstructed and modernised to meet the demands of both passenger and freight traffic. The design speed is 200 km/h for Sub-section 3.1 and 160 km/h for Sub-section 3.3. On Sub-section 3.1, works include 12 grade-separated crossings, 8 bridges and culverts, 2 pedestrian underpasses, 1 retaining wall, and 17 culvert structures beneath the railway track. On Sub-section 3.3, works include 18 grade-separated crossings, 14 bridges and culverts, 2 pedestrian underpasses, 15 retaining walls, 18 culvert structures beneath the railway track, and 2 culvert structures beneath roadways. Across both Sub-sections 3.1 and 3.3, works include reconstruction of the existing and construction of new overhead contact line (OCL) systems, as well as electrical power installations in stations, tunnels and tunnel entrances, energy facilities, relay stations, sectioning posts (including those with neutral sections), remote control systems for electric traction installations, transformer stations supplied from OCL, and lighting of grade-separated crossings and access roads. During the execution of signalling works in stations, automatic switching of turnouts and train routes will not be possible. Due to the shutdown of station signalling systems, operations will be adapted to a temporary mode. Inter-signal interlocking devices (UMZ) will be used, installed in temporary rooms for train dispatchers, with traffic managed within station areas. Some limited works on neighbouring sections may be included in the scope of the contract.

Original sector

Construction work

Location

Country

Serbia

Source

Source

TED Europa

URL

More Details

Record type

Tender

Sector

Power Generation (CCGT), Mass Transit, Rail, Tunnel, Road

Article published date

2026-05-26

More on this tender

Research

Free account

View all details

You are reading the public part. A free account opens the rest:

  • Every detail on this tender
  • News and media coverage
  • Technical research
View all details

Free account · no card · lands you back on this tender