Z1Da--Nrm Construction -528A8-18-801 Renovate For Cardiac Cath & Ir

Sector: Cement • Location: United States of America

Source: SAM.gov

Tender
Solicitation

This amendment answers the following vendor questions: Is lead lining required for the concrete floor in the space? Specifications call for installation of floor lead. See Physicists report Please advise. Answer: The installation of lead lining is not necessary as the existing concrete is thick enough. If flooring concrete/topcoat removal is required during construction, the contractor shall retu

Status
Closed
Sector
Cement, Commercial, Steel, Residential
Location
United States of America
Updated
3 Nov 2026
Source
SAM.gov

ConstructChat

Ask ConstructChat about Z1Da--Nrm Construction -528A8-18-801 Renovate For Cardiac Cath & Ir

Pick a question to edit it, or write your own.

First answer free · no account

I am a

Tender Information FAQ

Tender Information

3 Q
The tender “Z1Da--Nrm Construction -528A8-18-801 Renovate For Cardiac Cath & Ir” is a tender record in Taiyo, linked to the Cement sector. It is issued for works, goods, or services related to United States of America.

Participants

Not available for this record.

Status

Original status

solicitation

Taiyo status

Closed

Taiyo last update

2026-11-03

Contact

Not available for this record.

Description

Description

This amendment answers the following vendor questions: Is lead lining required for the concrete floor in the space? Specifications call for installation of floor lead. See Physicists report Please advise. Answer: The installation of lead lining is not necessary as the existing concrete is thick enough. If flooring concrete/topcoat removal is required during construction, the contractor shall return the impacted area back to its original specifications. Who is responsible to remove the office furniture that is currently in the construction space? Answer: The VA shall be responsible for the removal of office furniture and other misc. items stored in the construction area. For the above ceiling structural steel install in the 1st floor lobby: Who will be responsible to rework the existing ductwork, piping, sprinkler, electrical conduit, etc. so that the steel can be installed? Answers: Rework of the existing ductwork, piping, sprinkler, electrical conduit, etc. so that the steel can be installed shall be the responsibility of the contractor Will construction fence need to be installed around the contractor laydown staging area? Answer: Yes Will construction fence need to be installed around the exterior area of the scaffolding entrance Answer: Yes This amendment changes the RFI deadline date listed in block 10 of the SF1442 from 03/05/2026 at 12:00EST to 03/13/2026 at 12:00EST. This amendment changes the close date of this solicitation listed in blocks 10 and 13a of the SF1442 from 03/17/2026 at 12:00EST to 03/124/2026 at 12:00EST. All other terms and conditions remain the same.

Original sector

Construction

Location

Country

United States of America (USA)

Source

Source

SAM.gov

URL

More Details

Record type

Tender

Sector

Cement, Commercial, Steel, Residential

Article published date

2026-03-07

More on this tender

Research

Free account

View all details

You are reading the public part. A free account opens the rest:

  • Every detail on this tender
  • News and media coverage
  • Technical research
View all details

Free account · no card · lands you back on this tender